India’s first bullet train service is expected to begin operations in the last quarter of 2027, with the initial section of the Mumbai-Ahmedabad High-Speed Rail Corridor set to connect Surat and Vapi.
Railway Minister Ashwini Vaishnaw confirmed the timeline on 20 November, saying the service would be introduced in phases. The full corridor, which spans approximately 508 kilometres, will connect Mumbai in Maharashtra with Ahmedabad in Gujarat.
The project marks India’s entry into high-speed rail operations and is being developed with technical support from Japan. Once completed, the corridor is expected to reduce travel time between Mumbai and Ahmedabad to around two hours.
Vaishnaw also outlined the progress of construction. As of September 2026, approximately 456 kilometres of pier work and 371 kilometres of viaduct construction had been completed. Noise barriers had been installed along 299 kilometres, while work on stations, tunnels and other infrastructure continued.
The corridor includes a 21-kilometre tunnel in Maharashtra, of which around seven kilometres will pass beneath Thane Creek. It will be India’s first undersea rail tunnel.
The project is designed for an operational speed of 320 kilometres per hour, with a design speed of 350 kilometres per hour. It is expected to introduce new standards in railway technology, safety and passenger travel.
The initial Surat-Vapi service will be followed by the opening of additional sections as construction and testing progress.